Magnolia Creek and Cedar Gully Channel Improvements (Phase I and II)
Budget
$7.6 million
Scope of Work
Phase I: Improve waterway flowing into existing ponds in Westwood and Magnolia Creek, modify culvert on Summer Place to better control flow rates.
Phase II: Regrade slopes, revegetate area, and install erosion control measures.
Subdivisions, Areas, or Streets Impacted
Countryside, Rustic Oaks, Westover, Westwood, Magnolia Creek, Villages of Oak Creek
Magnolia Creek Public Meetings
- Magnolia Creek and Cedar Gully Channel Improvements Public Meeting Presentation - April 8, 2021 (PDF)
- Magnolia Creek and Cedar Gully Channel Improvements Public Meeting Video of Presentation - April 8, 2021
- Magnolia Creek and Cedar Gully Channel Improvements Public Meeting Presentation - June 13, 2019 (PDF)
- Magnolia Creek and Cedar Gully Channel Improvements Public Meeting Video of the Presentation - June 13, 2019
Project Status as of August 2022
The consultant provided a hydrologic and hydraulic model and study for the watershed using the Houston-Galveston Area Council (H-GAC) aerial topographic information provided by the Texas Natural Resources Information System (TNRIS) and field observations. A drainage area map for Magnolia Creek and Cedar Gully Channel was also provided showing the watershed and sub-basin delineation in an effort to provide the best recommendation for adequate drainage flow. The United States Army Corps of Engineers published the Magnolia Creek Individual Permit public notice in early July. The City is expecting to receive an update by mid-August from the consultant on the USACE’s response.
Original Schedule
The original schedule, as of September 2019, shows preliminary design programmed in quarter 4 of 2019 and quarter 1 of 2020 for Magnolia Creek and Cedar Gully Channel Improvements, Ph I & II. Design is programmed for quarter 3 of 2021 through quarter 2 of 2022. Permitting phase programmed for quarter 2 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2022 with construction following through quarter 4 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
The current schedule, as of December 2021, for the Magnolia Creek and Cedar Gully Channel Improvements, Phase 1 and 2 project shows preliminary design in progress from quarter 4 of 2019 through quarter 4 of 2020. Final design is programmed for quarter 1 of 2022 through quarter 4 of 2022. Permitting is now in progress from quarter 4 of 2020 through quarter 2 of 2023. Construction bidding is programmed for quarter 2 of 2023. Construction is programmed for quarter 3 of 2023 through quarter 3 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Project Manager Contact Information
- James Doyle
Phone: 281-554-1454
Email James Doyle