Bay Colony Area Detention Modifications

Budget

$3.2 million

Scope of Work

Widen existing detention basins and drainage channels in the Bay Colony area to add storage capacity to reduce the potential impact of flooding.

Subdivisions, Areas, or Streets Impacted

Bay View, Bay Colony Parkside, Lakes in Bay Colony, Enclave at Bay Colony, Meadows in Bay Colony, Centerfield Lakes, Dove Meadows, Retreat in Bay Colony, Bay Colony Pointe, Bay Colony Point West, Enclave at Bay Colony West, Bay Colony Meadows West, Tallow Forest, and Mary Lane

Aerial Map of Bay Colony Area Detention Modifications with Project Boundaries

Bay Colony Area Detention Modifications aerial map

Bay Colony Area Detention Modifications timeline schedule

Project Status as of June 2023

G.W. Phillips Concrete Construction, Inc. was awarded the construction contract at the April 12, 2022 City Council meeting. The contractor mobilized to the site at the end of June 2022. Grading work on the ponds at Bay Colony Town Center, Bay Colony Parkside Community, Bay Colony Meadows East Detention Pond and Bay Colony Pointe Subdivision ponds is complete. Grading improvements to over 90% of the ponds has been completed, including at Bay Colony Town Center, Bay Colony Parkside Community, Bay Colony Meadows East Detention Pond, Bay Colony Pointe Subdivision and Lakes of Bay Colony. The contractor is currently working on the ponds at Meadows of Bay Colony and completing restoration of all ponds associated with the project. The project is expected to reach substantial completion this summer.

Original Schedule

The original schedule, as of September 2019, shows design programmed from quarter 4 of 2019 through quarter 1 of 2020 for Bay Colony Area Detention Improvements. Land acquisition is programmed from quarter 2 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, for the Bay Colony Area Detention Improvements project shows design in progress from quarter 4 of 2019 through quarter 3 of 2021. Land acquisition and permitting was programmed from quarter 3 in 2020 through quarter 3 of 2021. Construction bidding is programmed in quarter 4 of 2021 through quarter 1 of 2022. Construction in progress from quarter 2 of 2022 through quarter 2 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.