Budget
$223,000
Scope of Work
The goal of this project is to improve drainage within the subdivision by reestablishing and widening existing drainage swales and outfalls.
Subdivisions, Areas, or Streets Impacted
Countryside


Project Status as of August 2022
The City is looking to hold a public meeting with the impacted homeowners by end of August or early September. Pending the outcome of the public meeting, the project will be advertised for bid by mid to end of September 2022.
Original Schedule
As of September 2019, it shows design in progress in quarter 1 of 2020 through quarter 2 of 2021 for Countryside Subdivision Drainage Improvements. Land acquisition is programmed from quarter 3 of 2020 through quarter 2 of 2021. Construction bidding is scheduled for quarter 3 of 2021 with construction following through quarter 4 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
The current schedule, as of June 2021, for the Countryside Subdivision Drainage Improvements project shows design in progress from quarter 4 of 2019 through quarter 2 of 2021. Land acquisition is shown in progress from quarter 4 of 2020 through quarter 3 of 2021. Construction bidding is programmed for quarter 3 of 2021. Construction is programmed for quarter 4 of 2021 through quarter 4 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Project Manager Contact Information
Susan Oyler
Phone: 281-554-1453
Email Susan Oyler