- Home
- Departments
- Project Management
- 2019 Bond Program
- Proposition A
- Dove Meadows Detention Pond
Dove Meadows Detention Pond
Budget
$5.3 million
Scope of Work
Purchase land and construct a 115 acre-foot detention pond east of Blue Wing Drive and west of Borden’s Gully.
Subdivisions, Areas, or Streets Impacted
Dove Meadows
Project Status as of June 2023
Construction started on September 26, 2022. The contractor is continuing the excavation of approximately 130,000 cubic yards of dirt from the site to construct the detention pond to create added capacity. The contractor completed the excavation of the shelf-cut area along Borden’s Gully in January and constructed the concrete weir in February. Forming and pouring of the pilot channels will be ongoing. Rain has slightly delayed this project, along with the relocation of the water line which was unforeseen. Contractor is performing restoration work and re-vegetation of the site to prepare for substantial completion but the pond is functioning as designed! Expected completion of this project is Summer 2023
Original Schedule
As of September 2019, shows design in progress in quarter 2 of 2019 through quarter 3 of 2020 for Dove Meadows & Borden's Gully Detention Pond. Land acquisition is programmed from quarter 1 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 1 of 2021. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
As of March 2021, for the Dove Meadows & Borden's Gully Detention Pond project shows design complete from quarter 2 of 2019 thru quarter 1 of 2021. Final design is programmed for quarter 4 of 2021. Land acquisition is shown in progress from quarter 1 of 2020 through quarter 3 of 2021. Permitting is shown in progress from quarter 4 of 2020 through quarter 3 of 2021. Construction bidding is in programmed for quarters 1 & 2 of 2022. Construction is programmed for quarter 3 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Project Manager Contact Information
- James Doyle
Phone: 281-554-1454
Email James Doyle