FM 518 and Wesley Drive Drainage Improvements

Budget: $3 million

Scope of work: Reconstruction of portions of Wesley Drive for improved drainage to Corum Ditch. Purchase land and construct detention pond near Wesley Drive and Corum Ditch.

Subdivisions, areas, or streets impacted: Main Street, Highland Terrance subdivision, Calder Road (east of I-45), Wesley Drive and Pecan Drive areas

map

project timeline-fm518 and wesley drive drainage-01

Project Status as of August 2022

A revised environmental proposal was approved by a change order on March 28, 2022, along with a 150 day extension for a modified Environmental Assessment required by the General Land Office (GLO) to meet HUD and FEMA requirements.
A meeting was held with TxDOT and the consultant on June 21, 2022, to discuss the 60% design plans. On July 12, 2022, TxDOT contacted the project’s consultant to relay that this should be a TxDOT project and not a League City project since the majority of the project is in the TxDOT right-of-way. City staff will be meeting with the TxDOT Area Office Engineer in late August to discuss how the project will move forward. The consultant is continuing with their design and expects to deliver the 90% design plans in late summer 2022.

Original Schedule

The original schedule, as of September 2019, shows design programmed in quarter 4 of 2021 through quarter 2 of 2022 for FM518 & Wesley Dr. Drainage Improvements. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, for the FM518 and Wesley Dr. Drainage Improvements project shows the grant application complete from quarter 1 of 2019 through quarter 2 of 2020. Grant award was complete in quarter 3 through 4 of 2020 with grant kickoff completed in quarter 1 of 2021. RFQ for design services required by the grant complete in quarter 2 of 2021. Design is programmed from quarter 3 of 2021 to quarter 2 of 2022. Construction bidding is programmed for quarter 3 of 2022. Construction is programmed for quarter 4 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Project Manager Contact Information

Danny Carder
Phone: 281-554-1443
Email Danny Carder