Budget
$50,000
Scope of Work
Improve drainage flow to Kelly’s Ditch.
Subdivisions, Areas, or Streets Impacted
Hidden Oaks area


Project Status as of December 2021
Staff reviewed 90% design plans and returned comments to engineer; design modifications based on landowners’ input being reviewed for level of improvement; City staff decided to complete design in-house based on homeowners input and request; City staff has design to 90%; working through a potential issue with a pipeline company; City staff is modifying design to accommodate pipeline restrictions.
Original Schedule
The original schedule, as of September 2019, shows design programmed in quarter 4 of 2019 through quarter 1 of 2020 for Hidden Oaks/Calder Rd. Drainage Improvements. Construction bidding is scheduled for quarter 2 of 2020 with construction following through quarter 3 of 2020. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
The current schedule, as of December 2021, for the Hidden Oaks/Calder Rd. Drainage Improvements Project shows contract design complete from quarter 4 of 2019 through quarter 2 of 2020. Details discovered during the design process made in-house design desirable, which began in quarter 3 of 2020 through quarter 1 of 2022. Construction bidding is programmed for quarter 1 of 2022. Construction is programmed for quarter 2 of 2022 through quarter 1 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.