Budget
$3.7 million
Scope of Work
Increase capacity and efficiency of drainage flows through Borden’s Gully to I-45.
Subdivisions, Areas, or Streets Impacted
Centerfield Lakes, Dove Meadows, Retreat in Bay Colony, Bay Colony Pointe, Bay Colony Pointe West, and Enclave at Bay Colony West


Project Status as of June 2023
Revised 30% design plans were received in October 2022 and design coordination between the City of League City and City of Dickinson design consultants progressed through April 2023. The City’s consultant was given authorization to proceed with 60% design in May 2023.
Original Schedule
The original schedule, as of September 2019, shows design programmed in quarter 4 of 2021 through quarter 2 of 2022 for Hughes Lane/W Deats Rd Culvert Crossing Improvements. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Current Schedule
The current schedule, as of March 2021, for the Hughes Lane/W Deats Rd Culvert Crossing Improvements project shows design in progress from quarter 4 of 2020 through quarter 2 of 2021. Construction bidding is programmed for quarter 4 of 2022. Construction is programmed for quarter 1 of 2023 through quarter 1 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.
Project Manager Contact Information
Susan Oyler
Phone: 281-554-1453
Email Susan Oyler