Grissom Road Reconstruction & North Service Area Waterline

GO Bond Funding: $9.3 million Grissom Road Reconstruction Project Sheet (PDF)

Scope of Work: 
This project replaces approximately 5,600 feet of an existing two-lane rural open ditch roadway with a four-lane divided urban roadway. It will provide a pedestrian sidewalk, as well as drainage mitigation required for increased runoff. This project will also include approximately 5,000 feet of 12-inch waterline from the North Service Area booster station to West NASA Road. The boundary of this project will run from Abigail Lane to the West NASA Road/Grissom Road intersection.

Subdivisions, Areas or Streets Impacted:
Shady Lane, Massengale Lane, W Nasa Rd., and Autumn Lakes

map

project timeline-grissom road-01

Project Status as of July 2022

Construction crews are installing the 16-inch and 8-inch force main along the north side of Grissom Rd. The new 16-inch force main will tie into the existing 16-inch force main south of Grissom Rd. It will travel north to the new Right-of-Way and then parallel the Right-of-Way to the lift station. The new 8-inch force main will continue to parallel the Right-of-Way to the lift station. Crews will then focus on finishing the installation of the storm sewer system. They are anticipating to start paving from the southwest moving northeast.

Council has awarded the construction contract to Tandem Services, LLC on February 22, 2022 with Notice to Proceed issued on April 11, 2022. Construction is expected to be complete by April 6, 2023.

Original Schedule

The original schedule, as of September 2019, shows the design phase of a Grissom Road Reconstruction in progress in quarter 2 of 2019 through quarter 2 of 2020. Land acquisition was planned for quarters 1 and 2 of 2020. Construction bidding is scheduled for quarters 3 and 4 of 2020 with construction following in quarter 1 of 2021. Construction is programmed from quarter 1 of 2021 through quarter 2 of 2022. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, shows the design phase for Grissom Road Reconstruction complete from quarter 2 of 2019 to quarter 4 of 2020. Land acquisition was complete from quarter 1 of 2020 to quarter 3 of 2021. Relocation of utilities in progress from quarter 3 of 2020 to quarter 1 of 2022. Construction bidding in progress for quarter 1 of 2022. Construction programmed from quarter 2 of 2022 through quarter 2 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.