Project Information
The Clear Creek Tributaries Select Clearing and Desnagging Project consists of the removal of vegetation and snags or other obstructions along Clear Creek to improve drainage and maintain flow capacity with the following channels:
- Magnolia Creek: FM 518 to Clear Creek (Estimated Construction Cost: $1,026,000)
- Cedar Gully: FM 518 to Magnolia Creek (Estimated Construction Cost: $507,300)
- Landing Ditch: FM 518 to Clear Creek (Estimated Construction Cost: $188,500)
- Newport Ditch: FM 518 to Landing Ditch (Estimated Construction Cost: $665,600)
Public Meetings
Project Status as of August 2022
The 100% design plans have been approved and are being prepared for signature. It is anticipated that this project will go out for bid in August.