Clear Creek Tributaries Select Clearing & Desnagging Project

Project Information

The Clear Creek Tributaries Select Clearing and Desnagging Project consists of the removal of vegetation and snags or other obstructions along Clear Creek to improve drainage and maintain flow capacity with the following channels:

  • Magnolia Creek: FM 518 to Clear Creek (Estimated Construction Cost: $1,026,000)
  • Cedar Gully: FM 518 to Magnolia Creek (Estimated Construction Cost: $507,300)
  • Landing Ditch: FM 518 to Clear Creek (Estimated Construction Cost: $188,500)
  • Newport Ditch: FM 518 to Landing Ditch (Estimated Construction Cost: $665,600)

Public Meetings

Project Status as of August 2022

The 100% design plans have been approved and are being prepared for signature. It is anticipated that this project will go out for bid in August.

Map of Magnolia Creek and Cedar Gully project limits.
Map of clear creek, landing ditch, and newport ditch project limits.

Project Manager Contact Information

James Doyle
Phone: 281-554-1454
Email James Doyle