Walker Street at SH 96 Intersection Improvements

Budget

$1.8 million 

Scope of Work 

This project consists of correcting cross grading issues through the intersection, extending the eastbound to northbound left turn lane, installing a new right turn lane for eastbound to southbound traffic, extending the westbound to southbound left turn lane, installing a new right turn lane for northbound to eastbound traffic, and installing a new right turn lane for southbound to westbound traffic.

Subdivisions, Areas, or Streets Impacted 

The intersection at Walker Street and SH 96 (League City Parkway)

Project Status as of May 2022

COVID, TxDOT, and design consultant delays have impacted the overall schedule of this project. Currently, the City is anticipating a 90% design submittal in May 2022, and we are in negotiations to acquire the necessary right-of-way for the additional turn lanes. The goal is to advertise this project for bid as soon as possible (once right-of-way is acquired and TxDOT permit released).

Project Manager Contact Information

Anthony Talluto
Phone: 281-554-1451
Email Anthony Talluto