SH 3 Lift Station Upgrade & Force Main Replacement

Budget

$843, 506

Scope of Work

The scope includes coating the interior of the wet well, replacing all existing piping, suction and discharge equipment, and installing new submersible pumps and controls. All existing piping is currently located inside the dry well section of the lift station. All new piping will be located above ground, thus eliminating confined space entry. New stainless-steel electrical panels, including a generator plug-in connection, will be included in the lift station upgrades.

Subdivisions, Areas, or Streets Impacted 

Site location is located off SH3

Project Status as of August 2023

Bypass pumping operations were put in place in early June. Demolition of the lift station piping and electrical components has been completed. Pavement within the lift station site has been completed.  Posts for perimeter fence have been installed and the 20-foot rolling gate is currently being fabricated by the contractor’s supplier. Lining of the interior well is forecasted to be complete in the next couple of weeks. Mechanical piping is currently being fitted and will be complete in the following weeks. Construction duration is scheduled to complete by December 2023, barring weather or unforeseen delays.

Project Manager Contact Information

Jaime Dino
Phone: 281-554-1487
Email Jaime Dino

Aerial Map of SH 3 Lift Station Upgrade & Force Main Replacement.

Aerial Map of SH 3 Lift Station Upgrade and Force Main Replacement with Project Boundaries.